Drove 30% Reduction in Plant Turnaround Time for Oil Sands Producer

Capabilities
Energy

Challenge

A leading oil sands producer was approaching its annual plant shutdown, an event requiring $80M in spend and 3+ weeks of significantly reduced production.

The company needed help to identify areas to significantly reduce the full plant turnaround time in order to reduce costs and realize improved production.

Approach

  • Reviewed shutdown worklist to identify critical path scope and key work orders

  • Developed pre-approved repair plans for common repairs to minimize repair plan turnaround time
  • Minimized cleaning scope based on optimized inspection plan
  • Identified 144 work orders to be deferred from event due to low priority
  • Optimized schedule and aligned focused resources to the critical path scope​

Results

Number 1

Reduced turnaround time from 23 days to 16 days

Number 2

Realized 1,120 Kb of net annual production uplift

Number 3

Reduced cost of overall shutdown event by $26.5M